A44 Noakes Bridge to The Farthings – Resurfacing – Change in Programme Dates

A44 – Noakes Bridge to The Farthings, Near Bromyard – Revised dates

Monday, 16 November 2020 to (and including) Wednesday, 18 November 2020

Road closed 09.00 hours to 17.00 hours daily

Unfortunately due to several members of one of our sub contract crews being forced to isolate because of Covid-19, this is now having an impact on  works at Noakes Bridge.  Therefore, works will be suspended in the interim but I can confirm that another crew will resume works starting next Monday, 16 November 2020 and are scheduled to be completed by Wednesday, 18 November 2020.

In the meantime, we have instructed our traffic management and civils contractor to carry out regular checks of the site to ensure all signage and any ramping is adequate and remains safe at all times.

Please accept our apologies for this inconvenience.

Julia Lawrence

Works Control Manager | Balfour Beatty | Services | Living Places